About Atlantic Preserve
   Home > Review Process

Comprehensive Plan Review Process

  Date Process
Icon Page
June 2007 Florida Department of Community Affairs (DCA) issues Objections Recommendations and Comments (ORC) report to Martin County Board of County Commissioners (BCC).
Arrow Bullet


DCA had no comments or objections to the text amendment that created the policy allowing the donation of land in exchange for converting a portion of the Secondary Urban Services District (SUSD) to Primary Urban Services District (PUSD).
Arrow Bullet




DCA objects to land use amendment due to concerns regarding adequate water supply and wastewater treatment capacity. Requests additional information from the local utility provider (i.e. South Martin Regional Utility) to document adequate capacity.
Icon Page
July 2007 Letter submitted to BCC (pdf) responding to the ORC report and requesting that staff move the request to the next year’s set of Comprehensive Plan amendments (CPA) to provide sufficient time to resolve wastewater treatment capacity issues.
Icon Page
August 7, 2007 BCC votes to move the proposed CPA to next year’s amendment cycle (2008).
Icon Page
October, 2007 Submission of additional information to Martin County to address water supply and wastewater treatment capacity issues.
Icon Page
January 2008 Staff prepares updated report and recommendation for Local Planning Agency (LPA) public hearing.
Icon Page
February 2008 LPA conducts public hearing to re-evaluate CPA application.
Icon Page
May 2008 BCC conducts public hearing to transmit CPA to DCA.
Icon Page
September 2008 DCA issues ORC report.
Icon Page
December 2008 BCC final adoption hearing.

 

Planned Unit Development (PUD) Review Process

  Date Process
Icon Page
February 26, 2007 PUD application submitted to Martin County.
Icon Page
June 26, 2007 Received first staff report (pdf).
Icon Page
June – Oct. 2007 Evaluation of water, wastewater and traffic issues.
Icon Page
October, 2007 Resubmit additional information in support of PUD application.
Icon Page
January 2008 Receive revised staff report.
Icon Page
February 2008 Submit final plans for Phase 1.
Icon Page
June 2008 Receive final staff report and recommendation.
Icon Page
September 2008 LPA public hearing.
Icon Page
December 2008 BCC public hearing - final adoption.
Icon Page
January 2009 Donation of Property.
Icon Page
March 2009 Construction begins.
Icon Page
January 2010 Home sales begin.
Icon Page
2015 Community completed.

 

Back to top