July 2007 |
Letter submitted to BCC (pdf) responding to the ORC report and requesting that staff move the request to the next year’s set of Comprehensive Plan amendments (CPA) to provide sufficient time to resolve wastewater treatment capacity issues. |
|
August 7, 2007 |
BCC votes to move the proposed CPA to next year’s amendment cycle (2008). |
|
October, 2007 |
Submission of additional information to Martin County to address water supply and wastewater treatment capacity issues. |
|
April 29, 2008 |
BCC conducts public hearing to transmit CPA to DCA. |
|
August 2008 |
DCA issues ORC report. |
|
December 2008 |
BCC final adoption hearing. |
|
Planned Unit Development (PUD) Review Process
| |
Date |
Process |
|
February 26, 2007 |
PUD application submitted to Martin County. |
|
June 26, 2007 |
Received first staff report. |
|
July-October 2008 |
Evaluation of water, wastewater and traffic issues. |
|
October, 2008 |
Resubmit additional information in support of PUD application. |
|
January 2009 |
Receive revised staff report. |
|
June 2009 |
Submit final plans for Phase 1. |
|
October 2009 |
Receive final staff report and recommendation. |
|
December 2009 |
LPA public hearing. |
|
February 2010 |
BCC public hearing - final adoption. |
|
February 2010 |
Donation of Property. |
|
April 2010 |
Construction begins. |
|
January 2011 |
Home sales begin. |
|
2016 |
Community completed. |
|

|
|
|
|