  Date Process
Icon Page
July 2007 Letter submitted to BCC (pdf) responding to the ORC report and requesting that staff move the request to the next year’s set of Comprehensive Plan amendments (CPA) to provide sufficient time to resolve wastewater treatment capacity issues.
Icon Page
August 7, 2007 BCC votes to move the proposed CPA to next year’s amendment cycle (2008).
Icon Page
October, 2007 Submission of additional information to Martin County to address water supply and wastewater treatment capacity issues.
Icon Page
April 29, 2008 BCC conducts public hearing to transmit CPA to DCA.
Icon Page
August 2008 DCA issues ORC report.
Icon Page
December 2008 BCC final adoption hearing.

 

Planned Unit Development (PUD) Review Process

  Date Process
Icon Page
February 26, 2007 PUD application submitted to Martin County.
Icon Page
June 26, 2007 Received first staff report.
Icon Page
July-October 2008 Evaluation of water, wastewater and traffic issues.
Icon Page
October, 2008 Resubmit additional information in support of PUD application.
Icon Page
January 2009 Receive revised staff report.
Icon Page
June 2009 Submit final plans for Phase 1.
Icon Page
October 2009 Receive final staff report and recommendation.
Icon Page
December 2009 LPA public hearing.
Icon Page
February 2010 BCC public hearing - final adoption.
Icon Page
February 2010 Donation of Property.
Icon Page
April 2010 Construction begins.
Icon Page
January 2011 Home sales begin.
Icon Page
2016 Community completed.

 